Project scope and technical details:
- Pulverized coal fueled boiler with 2400 PSI/1050F/1050F steam cycle
- Air Separation Unit (ASU)
- Compression and Purification Unit (CPU)
- 100MW net electric output
- Heat integration of the ASU and CPU with the steam cycle
- Near Zero Emissions Plant (NZEP) for SO2, NOx, PM and Hg
- Low raw water usage with dry cooling
- High altitude operation
- Zero Liquid Discharge
- Mine-mouth site using low-rank sub-bituminous Powder River Basin coal
- 1 million tons/year CO2 storage
- Use CO2 for EOR or deep saline storage